Residential, Almaty
Almaty North Residences
- Employer
- Residential developer
- Area
- 96,000 m²
- Floors
- 18
- Duration
- 34 months
- Planned handover
- 15.09.2025
- Actual handover
- 24.09.2025
9 days late
A four-block residential project, handed over nine days late.
The project contains 720 apartments in four blocks. Structure and facade finished on their planned dates.
The lift supplier slipped by three weeks in June 2025. We reported it to the employer the same week and cut it to nine days with a recovery plan. The record shows it as a late handover.