The facade of a residential block with balconies.

Residential, Almaty

Almaty North Residences

Employer
Residential developer
Area
96,000 m²
Floors
18
Duration
34 months
Planned handover
15.09.2025
Actual handover
24.09.2025

9 days late

A four-block residential project, handed over nine days late.

The project contains 720 apartments in four blocks. Structure and facade finished on their planned dates.

The lift supplier slipped by three weeks in June 2025. We reported it to the employer the same week and cut it to nine days with a recovery plan. The record shows it as a late handover.